Project: Hülskens

Location: Wesel

In Operation

Staffing: 6 workers, 1 mobile excavator, 1 lifting platform, 2 truck cranes

Numbers: approx. 750 tons of scrap, 1 gravel plant

Project duration: about 1 month

The project at the Hülskens company in Wesel was completed in September 2020 and had a project duration of approximately one month. Among other things, five workers, a mobile excavator, a lifting platform and two truck-mounted cranes were used.

OUR LAST PROJECTS

Project: DM Stahl

The project at the company DM Stahl in Hagen was completed in May 2020 and had a project duration of 4 days. Among other things, five workers and a mobile excavator were deployed.

Project: Hülskens

The project at the Hülskens company in Wesel was completed in September 2020 and had a project duration of approximately one month. Among other things, five workers, a mobile excavator, a lifting platform and two truck-mounted cranes were used.

Project: DEMAG

The DEMAG project in Wetter was completed in May 2019 and lasted 18 days. Among other things, five workers, a lifting platform, a mobile excavator and a truck-mounted crane were deployed.

Project: EVONIK

The Evonik Infrastructure project in Marl was completed in June 2019 and lasted 4 days. Among other things, two workers and a lifting platform were deployed.